Stand at the end of the seawall in narragansett on a clear day and you cannot see them. the turbines of revolution wind stand in federal waters roughly 15 miles south of the coast, between martha's vineyard and block island, past the comfortable reach of landward eyes. what you can see is everything they set in motion: the dockets at the public utilities commission, the line on your bill that pays for the state's renewable standard, the lease blocks on federal charts that commercial fishermen still argue over.
This story is about the finish line. after a federal stop work order last august, a court fight in september, and first power this past march, the 65 turbine project is more than 90 percent complete, per the developer's construction updates, with full completion expected within the year. rhode island's name is on 400 megawatts of it under a 20 year contract. that makes this the rare energy story where the checkable milestones are public, recent, and close to home.
what got built, and when
revolution wind is a 704 megawatt project, developed by orsted with skyborn renewables (the project changed partners after eversource sold its offshore wind stake). its power is split under long term contracts: 400 megawatts to rhode island and about 304 megawatts to connecticut, enough for on the order of 350,000 homes, per the developer. rhode island selected its share through a competitive procurement in 2018, and state regulators approved the 20 year power purchase agreement with national grid on may 28, 2019. the electricity comes ashore at brayton point in somerset, massachusetts, and flows into the iso new england grid, the regional operator that balances supply and demand across the six states.
the scale is worth pausing on. block island wind farm, the five turbine, 30 megawatt project 3.8 miles off block island, entered commercial operation in december 2016 as the first commercial offshore wind farm in the united states, at a reported cost near $300 million. it ended the island's diesel habit and tied block island to the mainland grid. revolution wind is more than 20 times larger, and it is the reason the phrase offshore wind appears in rhode island law at all.

the stop work summer
on august 22, 2025, with the project roughly 80 percent built, the federal bureau of ocean energy management ordered construction halted offshore, citing national security. the order landed without a detailed public justification and threatened a project already carrying two states' contracts and, by the developer's account, thousands of construction jobs. on september 22, 2025, a federal judge in washington granted a preliminary injunction and lifted the order, finding the government's showing inadequate. work resumed within days.
the episode matters beyond this project. it showed that even a signed contract, a finished foundation program, and a decade of state and federal permits can be paused by a single discretionary order. for ratepayers, the practical risk was delay cost: offshore construction windows are seasonal, and a lost summer pushes completion, and the supply that comes with it, into the following year. the court's timing meant the project lost weeks, not a season.
what it means for your bill
the direct line from these turbines to your statement runs through the state's renewable energy standard, the law that requires rhode island's electricity supply to reach 100 percent renewable by 2033, enacted in 2022 under the act on climate. suppliers meet the standard by procuring renewable energy, and the cost surfaces on bills as a compliance charge. projects like revolution wind, with 20 year fixed contracts, are the kind of supply the standard is designed to pull into existence.
honesty requires the other half of the sentence. your bill is mostly not offshore wind. rhode island's supply rides the iso new england market, where prices follow natural gas, and the state's politics of energy are still shaped by the roughly 47 percent rate increase regulators approved in 2022. long term contracts are meant to steady costs over decades, not to reverse a winter's market spike. if someone tells you a single project will lower your bill next month, that claim does not hold. if someone tells you the 2033 standard is free, that does not hold either. the fair statement is narrower: revolution wind gives rhode island a large, fixed price, zero fuel cost block of supply, and the standard's costs and benefits land on your statement whether or not you watched the turbines go up.
what we are watching next
completion is the first item: the developer says the project finishes this year, and its construction updates page is the place to check that claim. second, the state's compliance filings under the 2033 standard, where the gap between today's supply mix and a fully renewable one gets counted in public. third, the quieter infrastructure story: block island's 2016 submarine cable enters its second decade, and the port of providence's shore power buildout for tugboats is the working waterfront's own small electrification, funded in part with federal grants. none of these moves fast. all of them are checkable, and we will keep the chart current as they do.
questions from readers
how big is revolution wind?
revolution wind is a 704 megawatt offshore wind farm in federal waters roughly 15 miles south of the rhode island coast, between martha's vineyard and block island. it has 65 turbines. rhode island holds a 20 year contract for 400 megawatts; connecticut holds the rest, about 304 megawatts.
why was construction stopped in 2025?
on august 22, 2025, the federal bureau of ocean energy management ordered the project to stop offshore work, citing national security. a federal judge lifted the order on september 22, 2025, granting a preliminary injunction after finding the government's justification inadequate. construction resumed within days.
is the project producing power now?
yes. per the developer's construction updates, revolution wind delivered first power in march 2026, had all 65 turbines installed, and was more than 90 percent complete as of september 2026, with full completion expected within the year. output figures vary with wind conditions; the developer's page is the source of record for milestones.
what does this mean for my electric bill?
the direct mechanism is the state's renewable energy standard, which requires rhode island's electricity supply to reach 100 percent renewable by 2033 and shows up on bills as a small compliance charge. long term contracts like the national grid agreement are intended to stabilize supply costs over 20 years, but near term bill levels depend on fuel markets and regional capacity costs that no single project controls.
what was the block island wind farm?
block island wind farm is the 30 megawatt, five turbine project 3.8 miles off block island that entered commercial operation in december 2016 as the first commercial offshore wind farm in the united states. its submarine cable ended the island's dependence on diesel generation and tied block island to the mainland grid.
sources of record
- revolution wind (revolution-wind.com), the developer's project and construction updates pages, operated by orsted and skyborn renewables. source of record for milestones: first power, turbine count, completion status.
- u.s. bureau of ocean energy management (boem.gov), the federal leaseholder's project and permitting record for the lease area south of rhode island, including the august 2025 stop work order.
- iso new england (iso-ne.com), the regional grid operator, for how the project's output enters the six state system.
- rhode island climate change office (climatechange.ri.gov), for the act on climate (2021) and the 100 percent renewable energy standard by 2033.
- rhode island office of energy resources (energy.ri.gov), for state procurement and renewable program context.
- orsted (orsted.com), corporate project materials for revolution wind's ownership and contract history.